The great thing about JMRI is that it is open source so you do not need to purchase it to get to play with any of its features. I use other open source programs like Libre Office, LibreCad, and Gymp which are all open source programs that are free.
It does take a bit of time to set it up very similar to creating all those car cards. The JMRI site gives you access to a very well written manual. Now I know most of us are men and do not need to read manuals "hahaha" but you do need to read this one, most likely a couple of times before you start. and a couple of times after that.
It does take a little maintenance but so does flipping all those car cards before each session. The purpose in using any computer program is to make repetitive tasks much easier and it does just that.
JMRI Operations generates manifests and switch lists for trains that are printed out on 1 or 2 pages, which is easier for new operators to use since they have a sheet that gives them instruction on what to do. There are even switch lists for the yard operators. They do not have to handle a stack of cards which for a 30 car train is about an 1 1/4 " thick and for the yard ops this can be huge. For example my yard is on the smaller side but still holds 70 cars. The other thing this does is tell operators exactly what track the cars are going to as you can see below in Melville. Below is a what a manifest for through freight 715 looks like. Rivers is in east staging and Watrous is west staging. The one thing that JMRI operations doesn't do well is block cars so I use this manifest to block the cars before a session starts. This is done in staging.
The first paragraph is mostly instructions I have added. This way even new ops have this with them all the time they are on this train.
Rivers is really just showing what cars and power 715 is leaving staging with and what track their train will be on. In this case the train will be on track 6.
Next it shows places they will pass and that there is no work there.
Then we get to Melville and it shows what pulls and spots there are and what tracks the cars are going to or coming from. The yard master will usually sort the pull cars ahead of time to a track and if busy the yard master can have the train drop all the cars to track 2 to keep things moving and move them later.
Watrous shows what cars you have and what track you are going to in staging. All my trains depart and arrive on the same track in staging. Each track just has different virtual names. Upon arriving in staging the train is reversed on the loop and then stored on its track. It will leave Watrous next trip as 716 east bound.
Manifest for train (715) West Through Freight
Valid 6/21/1959 17:29 (Tuesday)
At Rivers get your clearance, train orders and manifest
Drop cars to Track 2 at Melville and pick up cars from Track 3 West.
Or as instructed by Yard Master
At Melville take on fuel. Steamers can also take on water.
Get your clearance and train orders 10min crew change
Scheduled work at Rivers, departure time 07:00
[ ] Pick up CN 9030 F7A from Track 6
[ ] Pick up CN 9037 F7B from Track 6
[ ] Pull CN 478548 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull LNE 352 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 500799 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 485338 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 483916 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 544559 Boxcar 40' L< Boxes> from Track 6 -> Melville
[ ] Pull NYC 168265 Boxcar 40' L<Supliment> from Track 6 -> Melville
[ ] Pull GM&O 75003 Flatcar 40' L<Ties> from Track 6 -> Melville
[ ] Pull GTW 591599 Boxcar 50' L<Auto> from Track 6 -> Melville
[ ] Pull CN 479667 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 500899 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 526844 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull CN 543790 Boxcar 40' E<mpty> from Track 6 -> Melville
[ ] Pull NYC 712675 Gondola 52' E<mpty> from Track 6 -> Watrous
[ ] Pull CN 78934 Caboose 36' from Track 6 -> Watrous
Train departs Rivers Westbound with 15 cars, 792 feet, 830 tons
No work at Cana Jct
No work at Atwater
No work at Bangor Jct
No work at Waldron
Scheduled work at Melville, arrival time 07:30
[ ] Spot CN 478548 Boxcar 40' E<mpty> to Track 2
[ ] Spot LNE 352 Boxcar 40' E<mpty> to Track 2
[ ] Spot CN 500799 Boxcar 40' E<mpty> to Track 2
[ ] Spot CN 485338 Boxcar 40' E<mpty> to Track 2
[ ] Spot CN 483916 Boxcar 40' E<mpty> to Track 2
[ ] Spot CN 544559 Boxcar 40' L< Boxes> to Track 2
[ ] Spot NYC 168265 Boxcar 40' L<Supliment> to Track 2
[ ] Spot GM&O 75003 Flatcar 40' L<Ties> to Track 2
[ ] Spot GTW 591599 Boxcar 50' L<Auto> to Track 2 Ensure End Door Is Facing Ramp
[ ] Pull CN 110473 Hopper 40' E<mpty> from Track 3 West -> Watrous
[ ] Pull CN 533503 Boxcar 40' E<mpty> from Track 3 West -> Watrous
[ ] Pull CN 143201 Gondola 52' E<mpty> from Track 3 West -> Watrous
[ ] Spot CN 479667 Boxcar 40' E<mpty> to Track 5 Mixed East
[ ] Spot CN 500899 Boxcar 40' E<mpty> to Track 5 Mixed East
[ ] Spot CN 526844 Boxcar 40' E<mpty> to Track 5 Mixed East
[ ] Spot CN 543790 Boxcar 40' E<mpty> to Track 6
Train departs Melville Westbound with 5 cars, 354 feet, 372 tons
No work at Burmingham Jct
Scheduled work at Watrous, arrival time 21:12
Reverse Train Before parking
[ ] Set out CN 9030 F7A to Track 6
[ ] Set out CN 9037 F7B to Track 6
[ ] Spot CN 110473 Hopper 40' E<mpty> to Track 6
[ ] Spot CN 533503 Boxcar 40' E<mpty> to Track 6
[ ] Spot CN 143201 Gondola 52' E<mpty> to Track 6
[ ] Spot NYC 712675 Gondola 52' E<mpty> to Track 6
[ ] Spot CN 78934 Caboose 36' to Track 6
Train terminates in Watrous
In another post we will look at the paper work I use during operation sessions.
No comments:
Post a Comment